What is the procurement process in the automotive industry?

Short answer

In the automotive industry, procurement chooses part suppliers for a vehicle programme long before production, approves each part through APQP and PPAP, then orders by EDI call-offs, often just in time.

Cite this answereProcurement Toolkit, “What is the procurement process in the automotive industry?”, updated 7 Nov 2026, eprocurementtoolkit.org/guide/procurement-process-in-automotive-industry

Key takeaways

  • Automotive procurement buys parts for a vehicle programme: suppliers are chosen for a part of one model, long before the start of production, and then deliver it for as long as their agreement runs.
  • The supply chain is built in tiers: the carmaker (OEM) buys from Tier 1 suppliers, which buy from Tier 2, and so on. Quality and delivery rules pass down each tier.
  • A supplier is chosen through an RFQ and confirmed by a nomination, often a nomination letter, before production starts.
  • Before series supply, the supplier proves the part and its process through APQP and PPAP, and works under a quality system that meets IATF 16949.
  • In series production there is rarely one purchase order per delivery: the customer sends rolling delivery schedules and call-offs by EDI, and for some parts asks for just-in-time or just-in-sequence delivery.

What is the procurement process in the automotive industry?

The procurement process in the automotive industry is the way carmakers and their suppliers buy parts for a vehicle programme. A supplier is chosen by RFQ and nominated long before production, proves the part through APQP and PPAP, then delivers against rolling EDI delivery schedules and call-offs, often just in time.

The general steps of procurement, from need to payment, are the same in every industry; they are explained in the procurement process. What changes in automotive is the weight of direct materials, the long time between choosing a supplier and the first delivery, the formal approval of every part, and the way parts are ordered once production runs.

Materials weigh heavily in this industry. In the US Census Bureau’s 2021 survey of manufactures, the transportation equipment subsector (NAICS 336), which includes motor vehicles and their parts but also aircraft, ships and railway equipment, had the largest cost of materials of any subsector: $577.5 billion, against $878.7 billion of shipments, or about 66%. That is why most of automotive procurement is about direct parts.

General procurement and automotive procurement compared
PointGeneral procurementAutomotive procurement (direct parts)
Starting pointA requester states a needA vehicle programme with a planned start of production
Supplier choiceFor a purchase or a contract termFor one part of one model, under a long-term supply agreement
Award documentContract or purchase orderNomination letter or supply agreement, then orders and call-offs
Approval before supplySupplier onboarding, sometimes a sampleAPQP during development, PPAP and a signed part submission warrant
Quality systemISO 9001 often askedIATF 16949, plus each customer’s specific requirements
OrderingOne purchase order per needRolling delivery schedules and call-offs by EDI
DeliveryTo a stated dateTo the day or hour; for some parts in the sequence of the assembly line
Special assetsRareCustomer-paid tooling held by the supplier

Automotive procurement is general procurement stretched over a vehicle programme: a supplier is chosen once per part, approved formally, then ordered from by call-off, often daily.

Who buys from whom: OEMs and Tier 1, 2 and 3 suppliers

The carmaker is called the OEM (original equipment manufacturer). It buys systems and modules, such as seats, brakes or electronic units, from Tier 1 suppliers. A Tier 1 buys components, such as castings, cables or chips, from Tier 2 suppliers, which buy materials and smaller parts from Tier 3. Each tier runs the same procurement process towards the tier below.

Rules pass down the chain through purchasing conditions. A published example: the purchasing conditions for production material of AUO Mobility Solutions Germany, a supplier of parts for motor vehicles (version 09/2023), require suppliers to run a quality management system that “at a minimum meets the requirements of ISO 9001” and to develop it to “conform with IATF 16949”. The same conditions set how call-offs are accepted and who owns tools, two subjects covered below.

What are the steps of automotive procurement for a new part?

Steps of automotive procurement for a production part, from programme to end of production
StepWhat happensMain documents or standards
1. Programme and sourcing planThe OEM or Tier 1 lists the parts of a new model and decides which to make and which to buy, and from which kind of supplierBill of materials, timing plan, sourcing plan
2. Supplier panelOnly approved suppliers are invited to quote. Most are already on the buyer’s panel for the commodity; a new supplier registers on the buyer’s portal and is checked for quality capability firstSupplier portal, self-assessment, audit, IATF 16949 certificate
3. RFQ and quotationThe buyer sends drawings, volumes and timing; suppliers quote part price, tooling and often a cost breakdownRequest for quotation, cost breakdown, tooling quote
4. NominationThe buyer chooses one supplier per part and confirms it in writingNomination letter or supply agreement
5. Development (APQP)Supplier and buyer plan and check the part and the process up to launchAPQP plan, FMEA, control plan
6. Part approval (PPAP)The supplier submits evidence that the process makes good parts at the agreed rate; the buyer approvesPPAP package, part submission warrant (PSW)
7. Series supplyThe buyer sends delivery schedules and call-offs; the supplier ships and sends ship noticesEDI delivery schedules, call-offs, despatch advice
8. Receipt, invoice and paymentGoods are received against the call-off and the invoice is checked before paymentGoods receipt, invoice, payment
9. Changes and end of lifeEngineering changes, price reviews, end of series production, then service partsChange requests, new PPAP when the part or process changes

Steps 1 to 6 happen once per part, before the start of production; steps 7 and 8 repeat, often daily, for as long as the part is made.

How long steps 1 to 6 take varies by part and by carmaker; the APQP plan sets the dates for each part. The same steps apply to a Tier 1 buying from a Tier 2.

How is a supplier chosen: from RFQ to nomination

Suppliers first have to be on the list of those invited to quote. Vehicle makers run supplier portals for this. Scania, for example, tells new suppliers to register on the Volkswagen Group’s business platform for suppliers, which it uses “for sending out RFQ’s”; after evaluation a company may be added to the bidders lists for its material groups.

The request for quotation (RFQ) gives the drawings or specifications, the planned volumes per year, the timing and the quality and logistics requirements. The quotation usually separates the part price from the tooling price, and buyers often ask for a cost breakdown: material, processing, scrap, overhead, profit, packaging and freight. How an RFQ works in general is explained in what is an RFQ; how a buyer judges a cost breakdown is shown with a should-cost example in direct spend analysis.

The decision is the nomination: the buyer tells one supplier, in writing, that it will supply the part. The written form is often called a nomination letter. AUO’s purchasing conditions, for example, name “nomination letter, long-term agreement or other supply agreement” as the agreement that purchase orders and call-offs rely on, and require the supplier to deliver the ordered quantities and “the agreed capacities” set in it. A nomination is not a promise of volume unless the agreement says so; read what it commits each side to.

What are APQP and PPAP?

Both come from AIAG, the Automotive Industry Action Group, and are part of what the industry calls the core tools. Advanced product quality planning (APQP) is, in AIAG’s words, “a key automotive approach to move projects from concept to launch, minimizing lead times and startup issues”. It is the joint plan by which buyer and supplier develop a part and its production process: design reviews, risk analysis (FMEA), a control plan and checks at each gate.

AIAG announced the third edition of the APQP manual as available in March 2024. It adds “new sections on sourcing” and moves the control plan into a separate manual. AIAG said it was required by General Motors from 1 September 2024. Other carmakers set their own dates, so check each customer’s requirements.

The production part approval process (PPAP) is the formal approval of a part before series supply. AIAG’s fourth edition, from 2006, lists 18 elements, from design records and process FMEA to sample parts, and five submission levels. The summary document is the part submission warrant (PSW), signed by the supplier and approved by the customer. A new PPAP is needed when the part or its process changes. How buyers approve parts and follow defects is explained in supplier quality management.

For procurement, PPAP is also a commercial milestone. Nexteer Automotive’s tooling terms (2019), for example, say that unless agreed otherwise the supplier is paid in full for production tooling “after successful run-at-rate for the contracted capacity and Part Submission Warrant (PSW) full approval”.

What is IATF 16949, and why do buyers ask for it?

IATF 16949 is the quality management system standard of the automotive industry. It was written by the International Automotive Task Force (IATF), which VDA QMC describes as an international “ad hoc” group of national automotive industry associations and carmakers. The associations are AIAG (United States), ANFIA (Italy), FIEV (France), SMMT (United Kingdom) and VDA (Germany); the carmakers listed include BMW Group, Ford, General Motors, Mercedes-Benz, Renault, Stellantis and Volkswagen Group. The current version dates from 2016.

The standard is based on ISO 9001 and adds automotive requirements. The certification body NQA describes it as applicable to organisations that make components, assemblies and parts, covering “automotive production parts, service parts and related components”. BSI writes that certification “is mandatory throughout much of the global automotive supply chain”. Each carmaker also publishes customer-specific requirements, which a supplier must meet on top of the standard.

For buyers, the certificate is a gate before a supplier may quote for production parts. Some buyers accept ISO 9001 from a smaller supplier on condition that it works towards IATF 16949, as AUO’s conditions do. A certificate does not replace the buyer’s own audit of the specific process that will make the part.

How are parts ordered once production starts?

In series production, buyers rarely raise a purchase order for each delivery. The agreement for the part sets the price and terms; VDA 4901 notes that it usually states the expected quantity per part number for a period such as one year, which the supplier uses to plan capacity and to price. The buyer then sends rolling delivery schedules and call-offs by electronic data interchange (EDI). A delivery schedule gives planning quantities for the coming months (VDA gives six to twelve months as an example) that are not yet binding, so the supplier can plan; a call-off fixes what to ship, to the day or the hour. In Europe, the German association VDA publishes recommendations for these messages, based on the UN/EDIFACT standard, and Odette provides standards and tools for the European automotive supply chain. In North America, the ANSI X12 transaction sets are common.

Automotive delivery messages: VDA recommendations (EDIFACT) and the X12 sets with the same purpose
ProcessWhat the message saysVDA recommendation (EDIFACT message)X12 set with the same purpose
Delivery scheduleNet quantities per period over the coming weeks or months, with the cumulative quantity receivedVDA 4984 (DELFOR)830 Planning Schedule with Release Capability
Detailed call-offQuantities for the next days, to the day or hour; can be sent several times a dayVDA 4984 (DELFOR)862 Shipping Schedule
Just-in-time call-offFixed quantities and times; no deviation allowedVDA 4985 (DELJIT)862 Shipping Schedule
Just-in-sequence call-offParts in the order of the assembly lineVDA 4986 (DELJIT)866 Production Sequence
Despatch adviceWhat was shipped, in which packages, on which truckVDA 4987 (DESADV)856 Ship Notice/Manifest
InvoiceThe amount due for the deliveriesVDA 4938 (INVOIC)810 Invoice

The delivery schedule lets the supplier plan, the call-off tells it what to ship, and the despatch advice tells the plant what is coming; the X12 column pairs sets by purpose, not by an official mapping.

Three rules from VDA 4901, the VDA’s introduction to these messages, matter to buyers. New call-off quantities replace those sent before, so the latest message is the one that counts. Delivery schedules carry net requirements: the buyer has already deducted what it received, and sends the cumulative quantity received so the supplier can check. And if the supplier cannot deliver what is called off, it must tell the customer directly; EDI is not the channel for that.

Purchasing conditions often add a deadline for objections. AUO’s, for example, say a call-off needs no confirmation and is deemed accepted if the supplier does not object in writing within one working day of receipt. The ordering logic is close to a blanket purchase order with releases; the despatch advice, receipt and invoice then meet in the three-way match.

What are just-in-time and just-in-sequence delivery?

Just in time (JIT) means the plant keeps no stock of the part, only a small buffer at the line, and the supplier delivers the quantities needed for current production. VDA 4901 is strict: JIT call-offs allow no deviation in quantity or time, and the supplier must warn the customer of any shortage. The call-off can be pulled by actual use, as in a kanban system, where an empty container triggers the next delivery, or pushed by a plan, as with a pick-up sheet for a truck that collects at fixed times.

Just in sequence (JIS) goes one step further: parts arrive in the order of the cars on the assembly line. A seat supplier, for example, delivers seats in the colour and trim of each car in the order the cars will reach the seat station. VDA calls these production-synchronous call-offs, and notes that the sequenced call-off is the binding one under the purchasing and delivery conditions.

For procurement, JIT and JIS change what is bought. The buyer is not only buying a part at a price, but a delivery performance: rhythm, packaging, labels and the supplier’s distance from the plant. The conditions say what a late delivery costs. AUO’s, for example, make the supplier liable for damage caused by a missed date in a purchase order or rolling call-off, unless it shows it was not responsible, and allow the buyer to end supply agreements after repeated delays and a prior warning.

Who owns and pays for the tooling?

Many parts need tools made for that part only: moulds, dies, jigs, fixtures and gauges. Nexteer’s tooling terms define tooling as items made for “the manufacture of parts for specific models, assemblies, or products” with a normal life of one year or more. They expect the supplier to own its own machines, but where the buyer pays for the tooling, “the Buyer will own the Tooling”.

  • Ownership and marking. Customer-paid tools are marked as the buyer’s property and held by the supplier on a loan (bailment) basis. AUO’s conditions also ask that they be kept “visibly separate” from the supplier’s own assets.
  • Care and scrapping. AUO’s conditions make the supplier service the tools at its own cost and forbid scrapping them without written consent.
  • Payment. Tooling is often paid at a milestone; in Nexteer’s terms, after run-at-rate and full PSW approval.
  • Life. Nexteer’s terms ask that tools last for the life of the part, including service parts after series production ends.
  • Return. The buyer can recall its tools, for example to move the part to another supplier.

Keep a tooling register: tool number, part, supplier site, amount paid, ownership and condition. Without it, the buyer cannot move a part quickly when a supplier fails, because nobody knows which tools it owns or where they are.

How are prices managed over the life of a part?

The part price agreed at nomination is rarely fixed for the whole programme. Raw materials such as steel, aluminium, copper or resin move it up or down, often through an index clause; how such clauses work is explained in direct spend analysis. Engineering changes during the life of the model bring new quotations.

Some vehicle makers’ agreements also provide for yearly productivity price reductions. One published example: Commercial Vehicle Group, a supplier to commercial, construction and agriculture vehicle makers, states in its 2025 annual report that its arrangements with OEM customers “may provide for an annual prospective productivity price reduction”, calculated as a percentage of the previous year’s purchases. It says most of these reductions have been offset by its own cost reductions and help from its suppliers. Terms differ by carmaker and by part, so read each agreement rather than assume a rate.

Does automotive indirect procurement follow the same process?

No. Indirect purchases in a car plant, such as maintenance spares, IT, logistics services or facility services, follow the general process: requisition, purchase order, receipt and invoice, with catalogues for repeat items. They do not go through APQP or PPAP. Machines and production equipment bought for a new model sit in between: they are capital projects with their own acceptance tests. The difference between the two families of spend is explained in indirect procurement, and the analysis of maintenance spares in MRO spend analysis.

Questions

What is a nomination letter in the automotive industry?

It is the buyer’s written decision that a supplier will supply a part, usually for a vehicle programme. It refers to the purchasing conditions and sets the part, price, capacity and timing agreed. Purchase orders and call-offs then rely on it. Read what it commits each side to: it is not always a promise of volume.

Is IATF 16949 certification mandatory for automotive suppliers?

It is a private standard, not a law. Customers ask for it in their purchasing conditions, and BSI describes certification as mandatory throughout much of the automotive supply chain. Some buyers accept ISO 9001 from smaller suppliers on condition that they work towards IATF 16949.

What is the difference between a purchase order and a call-off in the automotive industry?

The purchase order or supply agreement sets the part, price and terms for a long period. The call-off, sent by EDI, tells the supplier what quantity to ship and when. One agreement can carry thousands of call-offs over the life of a model.

What is a Tier 1 supplier?

A Tier 1 supplier sells directly to the carmaker (OEM), usually systems or modules such as seats, brakes or electronic units. A Tier 2 supplier sells to a Tier 1, and a Tier 3 to a Tier 2. A company can be Tier 1 for one carmaker and Tier 2 for another.

What is the difference between APQP and PPAP?

APQP is the planning method that runs through the development of a part and its process, from concept to launch. PPAP is the approval at the end of that work: the supplier submits evidence, summarised in a part submission warrant, that its process makes good parts at the agreed rate.

New guides on eProcurement Toolkit

One short email when a guide on this line is added or revised. Nothing else.

Coming soon: sign-up opens with the first email.

Seb Troz

Source-to-pay consultant · written and maintained this guide

Seb Troz is a source-to-pay consultant who implements Ivalua for buying organisations. He writes the guides on eProcurement Toolkit from that hands-on work.

Disclosure: the author works as an Ivalua consultant. Pages that compare software say so next to the comparison.